Meeting Street Improvement Project

New sidewalks being installed as Meeting Street Improvement Project progresses

Meeting Street Improvement Project Update:

City of West Columbia image

Milestones

  • Demolition of the existing sidewalk on the eastbound side continues, with crews working toward 9th Street
  • Demolition and installation of new driveways at businesses continue
  • New sidewalk infrastructure has been installed and tested to make sure it meets plan specifications

What to Know

  • Sidewalks on the eastbound side of Meeting Street are closed. Please use the westbound sidewalks and use crosswalks safely.
  • Driveways to homes and businesses remain open and accessible. Driveway installation continues, with crews working in two sections.

Coming Up in the Next Two Weeks

  • All eastbound sidewalks will be closed as demolition continues
  • New sidewalk installation will begin as crews progress toward 9th Street

Questions or need assistance? Contact the City at [email protected] or (803) 939-8628.