Meeting Street Improvement Project Update:

Milestones
- Demolition of the existing sidewalk on the eastbound side continues, with crews working toward 9th Street
- Demolition and installation of new driveways at businesses continue
- New sidewalk infrastructure has been installed and tested to make sure it meets plan specifications
What to Know
- Sidewalks on the eastbound side of Meeting Street are closed. Please use the westbound sidewalks and use crosswalks safely.
- Driveways to homes and businesses remain open and accessible. Driveway installation continues, with crews working in two sections.
Coming Up in the Next Two Weeks
- All eastbound sidewalks will be closed as demolition continues
- New sidewalk installation will begin as crews progress toward 9th Street